Site Blueprint Demo

This is exactly what your field team receives. Redevv transforms engineering complex ISO drawings and BOQs into execution-ready job sheets in seconds.

AI Manpower Allocation

Smart crew sizing based on joint counts and pipe diameters.

Risk Management

Automated safety checklists and hold points for every joint.

Zero-Gaps Readiness

Dynamic material verification before the crew leaves the store.

Start Executing today

Join EPC leaders who are reducing project overheads by 34% with Redevv Core Intelligence.

Get Started Free
Logo

Rethela Technology Pvt Ltd

Nesco IT Park, Goregaon East, Mumbai, Maharashtra 400063

Job Execution Sheet

ID: RDV-JS-2026-0892

Scan to Track
Project NameRefinery Expansion - Phase II (Distillation Unit)
Line Number / Spool6"-CS-DU-102-S04 (Spool 04)
Date & Shift22/02/2026 | Day Shift (08:00 - 18:00)

Section 02: Scope Visual Reference

Engineering drawing thumbnails and ISO highlights are available in the digital twin. Refer to the scan link for details.

Section 03: Execution Parameters

Manpower1 Senior Fitter, 2 6G Argon Welder, 2 Grinder/Helper, 1 Rigging Supervisor
Readiness94% Verified
WorkfrontClearance Issued
Est. Duration1 Days

Section 04: Role-Based Execution Tasks

Package: Spool Assembly & Support Alignment0.5 Days

Senior Fitter/Rigger

1

Position Inlet Elbow using chain pulley block and verify level.

Ref: V-102-EL-01Tools: Spirit Level, Chain BlockSafety: Fall Protection
2

Tack weld support base to column structural ring.

Ref: S-102-SUP-ATools: Welding MachineSafety: Fire Blanket

6G Argon Welder

3

Perform root pass for Spool-to-Nozzle joint (Joint #J12).

Ref: J12-CSTools: Argon Torch, ER70S2 WireSafety: Flash Protection
Package: Final Welding & Quality Check0.5 Days

Senior Fitter

4

Align flange and verify bolt hole orientation and verticality.

Ref: FL-102-04Tools: Plumb Bob, Internal Alignment ClampSafety: Hand Protection

6G Argon Welder

5

Complete final hot pass and capping for Spool joints.

Tools: DC Inverter, Argon GasSafety: Fume Extraction

Supervisor

6

Visual inspection and dimension verification against ISO.

Tools: Measuring Tape, VernierSafety: Final Clearance

Section 05: Component Reference

Comp IDDescriptionLocation / Line Ref
V-102-EL-01Column Inlet Elbow (90 Deg)Elevation +12.5m
S-102-SUP-AH-Beam Pipe Support (Structural)Grid C-4
FL-102-04ANSI B16.5 Class 300 FlangeSpool End

Section 06: Material Checklist

[ ]Material NameReq. QtyAvail. QtyStatus
6" Sch 40 Carbon Steel Pipe (A106-B)4.5m4.5mReady
ANSI 300# SO Flange 6"2 Nos2 NosReady
Spiral Wound Gasket 6" SS3042 Nos1 NoPartial
ER70S2 Welding Filler Rod (Kg)1.52.0Ready

Section 07: Safety & Work Permit

Hot Work Permit issued and active for current shift.

PPE inspection completed for the entire execution crew.

Fire extinguisher and safety equipment verified at workfront.

Inspection Hold Points

  • Pre-Fitting Inspection
  • Root Pass Visual Clearance
  • Post-Weld Heat Treatment (if applicable)

Field Supervisor

Name: _______________________ Date: ________

Quality Assurance (QA)

Stamp / Sign: ________________ Date: ________